滁河圍堰施工方案0303
中交三航局寧滁快速通道及江星橋線改線工程項(xiàng)目部 滁河大橋主墩鋼板樁圍堰施工方案
目 錄
1、綜述 ...................................................................................................................................... 1
1.1 編制依據(jù) ..................................................................................................................... 1
1.2 適用范圍 ..................................................................................................................... 1
2、工程概況 .............................................................................................................................. 2
2.1 工程簡介 ..................................................................................................................... 2
2.2 滁河大橋概況 ............................................................................................................. 2
2.3 主墩概況 ..................................................................................................................... 2
2.4 工程地質(zhì) ..................................................................................................................... 2
3、主墩圍堰設(shè)計(jì)思路 .............................................................................................................. 2
4、施工組織 .............................................................................................................................. 3
4.1 施工部署 ..................................................................................................................... 3
4.2 主要施工機(jī)械 ............................................................................................................. 3
4.3 施工進(jìn)度計(jì)劃 ............................................................................................................. 4
更多內(nèi)容請?jiān)L問久久建筑網(wǎng)
5、鋼板樁圍堰施工方案 .......................................................................................................... 4
5.1 施工流程 ..................................................................................................................... 4
5.2 施工要點(diǎn) ..................................................................................................................... 5
6、承臺施工工藝 ...................................................................................................................... 8
6.1 施工工藝流程 ............................................................................................................. 8
6.2 承臺施工測量 ............................................................................................................. 8
6.3 基坑開挖及防護(hù) ......................................................................................................... 9
6.4 樁頭鑿除 ..................................................................................................................... 9
6.5 樁基檢測 ..................................................................................................................... 9
6.6 基底處理 ..................................................................................................................... 9
6.7 鋼筋制作綁扎 ............................................................................................................. 9
6.8 模板工程 ................................................................................................................... 12
6.9 混凝土澆筑 ............................................................................................................... 14
6.10 拆模及養(yǎng)護(hù) ............................................................................................................. 14
7、質(zhì)量控制及注意事項(xiàng) ........................................................................................................ 15
- i -
中交三航局寧滁快速通道及江星橋線改線工程項(xiàng)目部 滁河大橋主墩鋼板樁圍堰施工方案
8、安全措施 ............................................................................................................................ 16
9、文明施工與環(huán)境保護(hù) ........................................................................................................ 17
附件1:鋼板樁圍堰支撐平面布置圖 ................................................................................... 18
附件2:鋼板樁圍堰立面圖 ................................................................................................... 19
附件3:滁河大橋主墩鋼板樁圍堰計(jì)算書 ........................................................................... 20
附件4:承臺模板計(jì)算書 ....................................................................................................... 31
- ii -
中交三航局寧滁快速通道及江星橋線改線工程項(xiàng)目部 滁河大橋主墩鋼板樁圍堰施工方案
滁河大橋主墩鋼板樁圍堰施工方案
1、綜述
1.1 編制依據(jù)
1.1.1 招投標(biāo)文件
⑴ 《公路工程標(biāo)準(zhǔn)施工招標(biāo)文件 (2009年版)》(交公路發(fā)【2009】221號) ⑵ 《寧滁快速通道(浦合公路)南京段及江星橋線改線(星甸繞城段)投資建設(shè)(BT項(xiàng)目)招標(biāo)文件》
⑶ 《寧滁快速通道(浦合公路)南京段及江星橋線改線(星甸繞城段)投資建設(shè)(BT項(xiàng)目)投標(biāo)文件》。
1.1.2 工程承包合同
⑴ 《寧滁快速通道(浦合公路)南京段及江星橋線改線(星甸繞城段)投資建設(shè)合同書》
1.1.3設(shè)計(jì)文件
⑴ 《寧滁快速通道(浦合公路)南京段NC-NJ4施工標(biāo)段(K16+179.824~K17+014.904)施工圖設(shè)計(jì)》;
1.1.4 相關(guān)規(guī)范及驗(yàn)收標(biāo)準(zhǔn)
⑴《公路橋涵施工技術(shù)規(guī)范》(JTG/T F50-2011);
⑵《公路工程質(zhì)量檢驗(yàn)評定標(biāo)準(zhǔn)》(土建工程) (JTG F80/1—2004);
⑶《公路施工手冊》(橋涵);
⑷《鋼筋混凝土用熱軋光圓鋼筋》(GB 1499.1-2008);
⑸《鋼筋混凝土用熱軋帶肋鋼筋》(GB 1499.2-2007);
⑹《鋼筋焊接及驗(yàn)收規(guī)程》(JGJ 18-2003);
⑺《工程測量規(guī)范》(GB 50026-2007);
⑻《普通混凝土配合比設(shè)計(jì)規(guī)程》(JGJ 55-2011);
其它相關(guān)目錄標(biāo)準(zhǔn)、行業(yè)標(biāo)準(zhǔn)、技術(shù)條件及驗(yàn)收方法等。
1.2 適用范圍
用于指導(dǎo)寧滁快速通道(浦合公路)南京段滁河大橋主墩鋼板樁圍堰施工。
- 1 -
中交三航局寧滁快速通道及江星橋線改線工程項(xiàng)目部 滁河大橋主墩鋼板樁圍堰施工方案
2、工程概況
2.1 工程簡介
滁河大橋中心樁號K16+589.54,橋梁與路線正交。橋梁平面位于R=4000m的左偏圓曲線上。滁河航道等級為Ⅴ級航道,通航凈空為(6535)m,最高通航水位為9.374m。航道中心樁號為K16+589.5,路線與河道交角為73.2°,橋位處河口正寬130m,河道基本順直。 2.2 滁河大橋概況
主橋布跨為左幅:(48+85+52)m;右幅(52+85+48)m,左右幅錯(cuò)孔布置,采用分離式單箱單室預(yù)應(yīng)力連續(xù)箱梁,引橋采用25m裝配式部分預(yù)應(yīng)力混凝土連續(xù)箱梁。根據(jù)通航要求、規(guī)劃大堤堤頂通道凈空要求和臺后填土高度的控制,跨徑布置為(6325)+(7325)+(48+85+52)+(7325)+(6325)m,橋梁全長841.4m。 2.3 主墩概況
主橋橋墩采用斜布薄壁式墩,墩厚3.7m,承臺厚3m,基礎(chǔ)采用3排計(jì)9根υ1.5m鉆孔灌注樁基礎(chǔ)。主墩采用分離式承臺,滁河兩岸主墩14#、15#墩均位于水中。 2.4 工程地質(zhì)
根據(jù)設(shè)計(jì)院提供的工程地質(zhì)詳勘資料,主墩位置土層分布較均勻,兩岸主墩工程地質(zhì)差異不大。
各土層重力密度、粘聚力及內(nèi)摩擦角等參數(shù)詳見下頁表。
3、主墩圍堰設(shè)計(jì)思路
滁河兩岸主墩承臺尺寸為11m311m33m,為左右幅分離式承臺,綜合考慮圍堰打設(shè)方便、承臺模板安裝的作業(yè)空間,以及施工期間圍堰內(nèi)的抽水、集水井設(shè)置等因素,承臺周邊預(yù)留1.5m的作業(yè)空間,圍堰平面幾何尺寸為27.1m*18m,封底混凝土采用C15
- 2 -
中交三航局寧滁快速通道及江星橋線改線工程項(xiàng)目部 滁河大橋主墩鋼板樁圍堰施工方案 混凝土,厚度為50cm。
滁河最高水位為+6.50m左右,鋼板樁圍堰頂標(biāo)高為+7.50m,采用15m長拉森Ⅳ型鋼板樁,鋼板樁底標(biāo)高均為-7.50m,承臺底標(biāo)高為-0.411m,基坑底標(biāo)高為-0.911m,有效入土深度6.59m。根據(jù)受力計(jì)算,兩岸圍堰的內(nèi)支撐均設(shè)置2道,分別在+6.5m和+3.5m處。在圍堰的四個(gè)角各設(shè)置集水坑,采用水泵進(jìn)行抽水。
鋼板樁計(jì)算考慮的工藝:鋼板樁插打合攏后設(shè)置第1道支撐;繼續(xù)挖土至第2道支撐以下50cm,設(shè)置第2道內(nèi)支撐,繼續(xù)開挖至封底混凝土底標(biāo)高,抽出圍堰內(nèi)所有的水,干法澆筑封底混凝土。破除樁頭,樁基檢測合格后進(jìn)行承臺施工;而后進(jìn)行墩身及臨時(shí)支撐柱施工,并搭設(shè)0#塊支架。墩身及臨時(shí)支撐柱完工后,拆除第2道圍堰內(nèi)部支撐,搭設(shè)碗扣支架至第1道支撐,然后圍堰內(nèi)灌水至第1道支撐下部,拆除第一道支撐,后拔出鋼板樁。